91-1032 Makaaloa St #9B, Ewa Beach, HI 96706 · Report Date: April 6, 2026 · Prepared by Justin K. Taparra, NYG LLC

Welcome to your first renovation update. We officially kicked things off today with Andy on-site and work underway. Everything has gone smoothly so far. We came in under budget on materials, Andy's estimate came in lower than projected, and the property was clean and ready to go after Christian moved out. I'm excited to show you what we're building here. This report will come to you every week so you always know exactly where things stand.
This report covers everything that happened from March 25 through April 6, what's coming up in the next seven days, and where you stand right now on every open item. As always, I'm just a text or call away if you have questions about anything you see here.
March 25, 2026
April 6, 2026 — Today
April 20, 2026
38% Complete
You're 38% of the way through the project — Day 13 since the project kicked off on March 25. All pre-work milestones are done and contractor work is now officially underway. Here's a visual snapshot of where you stand on your renovation journey.
Since project start on March 25
Until target completion April 20
Out of 24 total renovation milestones
All pre-work done, contractor underway
Here's a detailed breakdown of everything that happened from project kickoff through today, day by day. Every item below represents real progress toward your finished unit.
NYG LLC project management agreement fully executed by both parties. Covers PM coordination at $75/hr (Justin) and $60/hr (Sam). No deposit required for PM services.
Detailed estimate request sent to our handyman/electrician Andy (Chi Tsou) covering all 22 renovation items. Included a video walkthrough of the unit so Andy could price everything accurately.
Sent you both the full renovation worksheet with our estimated costs for every item. Recommended completing all 22 items for the best return on investment. Estimated rental range after renovation: $2,250 to $2,450+ per month.
Samsung top load washer (white) and Samsung 7.2 cu ft gas dryer (white) ordered. Total with tax, delivery, haulaway, and all parts: $1,501.05. Delivery scheduled for April 30.
Chandelier, pendant lights, kitchen sink, kitchen faucet, ceiling lights (4-pack), bathroom vanity light, and a soap dispenser for the kitchen sink ordered. Total with tax: $628.26. All items shipping to Andy's home so he has materials ready.
Detailed recap email sent to you both with receipts attached and full breakdown of what was ordered and charged. Andy also notified that all Amazon materials are shipping to his house with estimated delivery dates for each item.
Andy returned his itemized estimate at $4,570.70 (including tax). This is $154.30 less than our original projection. Some items came in higher (security door, bathroom vanity, pocket door), but many more came in significantly lower, and the overall total is under budget. Full comparison was emailed to you both.
Christian vacated the unit on March 30. Property was left clean and ready for contractor access.
Lockbox placed on the front door for secure contractor access. Entry keys stored inside the unit with a copy in the lockbox.
Quick walkthrough with Uncle Warren and Auntie Sheri to check the unit after the tenant move-out and confirm everything looks good before work begins.
Andy is on-site today and renovation work is officially underway.
Justin took full before photos and video of every room. These will be used for the final before-and-after presentation at the end of the project.
A clear breakdown of where every dollar stands as of April 6, 2026. We came in under budget across the board.
A full overview of where every ordered item stands right now. Andy's own materials are being purchased separately and are covered by his estimate.
Arrived at Andy's house. Ready for installation.
Arriving at Andy's house. Andy can begin dining area light install.
3 pendant lights arriving at Andy's house.
Last major Amazon delivery. Andy can complete kitchen sink and faucet install after this arrives.
Arriving with one of the above batches.
Samsung washer and gas dryer delivered and installed. Plumber scheduled if needed for gas hookup.
Here's what's on the schedule for the week ahead. One financial deadline stands out — the rest are important milestones we're actively tracking and coordinating on your behalf.
Two important items happening tomorrow. First, Justin meets with Uncle Warren and Auntie Sheri at the unit at 12:30 PM to walk through the renovation progress and address any questions. After the property visit, we'll head to Justin's office to walk through how to file your GE taxes together.
Meet Justin at 91-1032 Makaaloa St #9B for a walkthrough of the unit and a progress check.
After the walkthrough, we'll go to Justin's office to walk through how to file your GE taxes together.
Bring any tax documents or questions you have for the GE tax session.
The dining area chandelier arrives at Andy's house. Andy can begin the dining area light install once it's in hand.
$2,285.35 is due by April 10 so Andy can purchase his remaining materials. Justin will coordinate the payment method (check or Venmo) and confirm with you before releasing. Do not send payment until Justin confirms directly with you.
The 3 kitchen peninsula pendant lights arrive at Andy's house. Justin will also conduct a mid-week check-in with Andy to confirm progress and flag any issues.
Combined Week 1 and Week 2 PM invoice. Approximately 1 hour logged so far as of April 6. Additional hours from this week will be included with GET tax.
Monitoring Andy's daily progress on the renovation
Coordinating material deliveries as they arrive at Andy's house
Tracking all receipts and costs for the end-of-project package
Preparing for the April 7 property walkthrough and GE tax session
Following up with Andy mid-week to confirm progress
Preparing the 50% deposit payment for Andy (due April 10)
Recording first weekly video update to send to you both
Meet at 91-1032 Makaaloa St #9B for a walkthrough, then head to Justin's office for GE tax help. Bring any tax documents or questions you have.
$2,285.35 is due by April 10. Justin will coordinate payment method (check or Venmo) and confirm with you before releasing. Do not send until Justin confirms.
Your complete renovation journey from project start to completion. Green = completed · Gold = active right now · Gray = ahead on the path.
Project management agreement executed. Work officially begins.
Detailed estimate request sent covering all 22 renovation items.
Full scope of work with estimated costs shared for your review and approval.
Samsung washer and gas dryer ordered from Lowe's. Delivery April 30.
Chandelier, pendant lights, kitchen sink, faucet, ceiling lights, vanity light, and soap dispenser ordered. Shipping to Andy's house.
Andy's estimate came in at $4,570.70, which is $154.30 under our projection. Approved and moving forward.
Christian vacated the unit. Property clean and ready for contractor access.
Lockbox on front door with entry keys. Secure access for Andy.
Walkthrough with Uncle Warren and Auntie Sheri. Andy officially begins renovation. Before photos and video captured.
12:30 PM at the property, then to Justin's office for GE tax walkthrough.
Dining area chandelier arrives at Andy's house.
$2,285.35 due so Andy can purchase remaining materials.
Kitchen pendant lights arrive. Mid-week progress check with Andy.
Combined Week 1 + 2 PM hours invoice with GET tax.
Last major Amazon delivery. Andy can complete kitchen sink and faucet install after this arrives.
Second progress check. All work should be wrapping up.
Room-by-room inspection. Test all electrical, plumbing, doors. Document any punch list items.
All 22 renovation items should be finished. Any punch list items resolved.
Walk the completed unit with Uncle Warren and Auntie Sheri. Get your sign-off that everything looks good.
Last invoice for remaining PM hours worked.
Remaining 50% balance paid after owner sign-off.
Polished before-and-after presentation delivered. Final walkthrough video sent.
Keys returned to owners or lockbox arrangements confirmed for next phase.
All PM work under this agreement is complete. Rental listing is a separate scope.
Samsung washer and gas dryer delivered and installed by Lowe's. Plumber scheduled if needed for gas hookup.

Every person on this list is working on your behalf. Don't hesitate to reach out — we're here for every question, big or small.
Project Manager NYG LLC 📞 (808) 349-6499 ✉️ justin@teamtaparra.com
Project Support NYG LLC ✉️ agent.care@teamtaparra.com
Handyman / Electrician 📞 (808) 683-9178 ✉️ andytsou222@hotmail.com License: EM-11118

Project Management · Justin K. Taparra, CEO & Owner
Questions? Call or text Justin anytime at (808) 349-6499 or email justin@teamtaparra.com. There's never a wrong time to reach out, Uncle Warren and Auntie Sheri. 🌺
Week 1 Renovation Update Hanoa Property